DV Program Activities
Select each DV Phase to view high-level activities connected with each phase of the DV review cycle.
Step | Responsible Party | DV Activities | Timeline |
---|---|---|---|
1 | SO | Select independent DVC based on Standards for Selecting a Data Validation Contractor (Appendix A). | December - March |
2 | DVC, SO | Notify CMS of DVC Selection/Request Access to Health Plan Management System (HPMS) Plan Reporting Data Validation Module (PRDVM). Enter/Update the DVC organization in HPMS. If applicable, enter/update the pre-assessment consultant in HPMS. | January - April |
3 | DVC, SO | Complete the web-based DV training. | February - March |
4 | DVC, SO | Review all DV documents. | January - March |
Note: References to December refer to the calendar year before the DV review. All other references to months refer to the same calendar year as the DV review.
Step | Responsible Party | DV Activities | Timeline |
---|---|---|---|
5 | SO | Complete Organizational Assessment Instrument (OAI), also known as Appendix E, and provide appropriate documentation to selected DVC per the OAI’s documentation request. | March - April |
6 | DVC, SO | Analyze OAI (Appendix E) Responses. | March or later |
7 | DVC, SO | Prepare for on-site or virtual visit (site visit agenda, resource needs, and logistics). | Early April |
8 | DVC, SO | Conduct on-site or virtual review (convene entrance conference, conduct interviews with SO staff, observe SO’s reporting processes, and obtain census and/or sample files). | Early April |
9 | DVC | Request additional documents following on-site or virtual visit (if applicable). | Mid/Late April |
Step | Responsible Party | DV Activities | Timeline |
---|---|---|---|
10 | DVC | Determine compliance with Data Validation Standards by recording findings in the Examination Engagement Standards (EES) (Appendix B). | April - June 15 |
11 | DVC | Submit EES findings to CMS via HPMS PRDVM and get DV scores. | No later than June 15 |
Step | Responsible Party | DV Activities | Timeline |
---|---|---|---|
12 | DVC, SO | Compile archive of DV work papers. | No later than June 15 |
13 | DVC | Provide draft findings to the SO. | No later than June 15 |
14 | DVC, SO | Review EES findings and make necessary technical and factual corrections. | No later than June 15 |
15 | SO | Appeal DV determinations (if applicable). | 5 business days following the DV deadline |