Reporting Findings for Standards Using Binary or Likert Scale
The table below shows examples of different scenarios a DVC might face and corresponding scores DVCs assign to the contract for the standards using Likert scoring.
Standard/ Sub-Standard | Percentage of Errors That the DVC Found in Plan Data | DV Response (DV Findings the DVC Reported on Column 'F' in Appendix B) |
---|---|---|
1.b, 1.c, 1.d, 2.a, 3.a, 3.b | More than 20% error in contract data for the given reporting section/data elements | 1 |
1.b, 1.c, 1.d, 2.a, 3.a, 3.b | Between 15.1% and 20% error in contract data for the given reporting section/data elements | 2 |
1.b, 1.c, 1.d, 2.a, 3.a, 3.b | Between 10.1% and 15% error in contract data for the given reporting section/data elements | 3 |
1.b, 1.c, 1.d, 2.a, 3.a, 3.b | Between 5.1% and 10% error in contract data for the given reporting section/data elements | 4 |
1.b, 1.c, 1.d, 2.a, 3.a, 3.b | 5% error or less in contract data for the given reporting section/data elements | 5 |